Tender Prices Rise 2.5 Times Faster Than Inflation

Tender prices rose well ahead of inflation in the year to 1 st quarter 2003, rising by 8.2%, compared with inflation of 3.3%, according to the latest issue of the BCIS Indices and Forecasts*. Tender prices in lst quarter 2003 also rose compared with the previous quarter, rising by 0.5%.

It should be noted that the sample received to date for I st quarter 2003 is quite small and the published figure is an estimate, therefore the index,for this quarter may vary more than is usually expected as the sample size improves.

Tender Price Update   Budget 2003
 
 
www.bccqs.co.uk - Building Cost Consultants - Quantity Surveying - Project Management
 
Building Cost Consultants
Quantity Surveying
Project Management
3 Exeter Drive
Glasgow G11 7UY

T. 0141 579 5900
F. 0141 579 5800

Neil B Hickey MRICS

E. info@bccqs.co.uk
W. www.bccqs.co.uk
  Home
About BCC
Projects History
Cost Information
Contact Us